earned value calculations
I have most of the values calculated. Looking for help with the rest…
Task | Budget Cost (PV) | Budget Duration | Status as of Week 13 | AC | EV | CV | CPI |
A | $5,000.00 | 2 | 100% | $5,000.00 | $5,000.00 | $0.00 | 1 |
B | $8,500.00 | 3 | 100% | $9,000.00 | $8,500.00 | -$500.00 | 0.944444444 |
C | $15,000.00 | 4 | 75% | $14,000.00 | $11,250.00 | -$2,750.00 | 0.803571429 |
D | $10,000.00 | 4 | 50% | $9,000.00 | $5,000.00 | -$4,000.00 | 0.555555556 |
E | $12,000.00 | 4 | 0% | $0.00 | $0.00 | $0.00 | 0 |
F | $15,000.00 | 5 | 0% | $0.00 | $0.00 | $0.00 | 0 |
TOTALS | $65,500.00 | $37,000.00 | $29,750.00 | -$7,250.00 | 0.804054054 | ||
CV = EV-AC | -7250 | Project is over budget | |||||
CPI = EV/AC | 0.804054054 |
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.